Celebratory Milestones#
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version 0b5c4af9, dated 2024-03-23. This corresponds to the status recorded in the project controls system for January 2024. This compares to December 2023.
Top milestones#
Code |
Name |
Due |
Previously |
---|---|---|---|
EPOC285 |
EPO Construction Finish |
2022-09-30 |
Completed |
T&SC-0400-1730 |
TMA Handoff to Rubin |
2023-03-31 |
Completed |
CAMM8090 |
COMP: Camera Pre-Ship Review at SLAC |
2024-04-25 |
2024-03-26 |
SUMMIT-Oct24-160 |
ComCam Reinstalled on TMA |
2024-06-26 |
2024-06-17 |
T&SC-1100-0400 |
3-Mirror Optical System Ready for Testing |
2024-07-05 |
2024-07-22 |
COMC-060200-20930 |
Camera Ready for Full System AI&T |
2024-10-08 |
2024-09-17 |
T&SC-0400-0950 |
Dome Complete |
2024-12-16 |
2024-12-16 |
SITCOM-122 |
LSSTCam Ready for On Sky (First Photon) |
2025-01-14 |
2025-02-19 |
LSST-1520 |
System First Light with LSSTCam |
2025-02-27 |
2025-04-04 |
LDM-503-17a |
Test report: Final Pipelines Delivery |
2025-06-25 |
2025-07-31 |
COMC-0654-0430 |
COMP: Science Validation Surveys Complete |
2025-06-25 |
2025-07-31 |
SITCOM-130 |
Operation Readiness Review Complete |
2025-07-02 |
2025-08-07 |
A public HTML version for embedding is here.
Supporting milestones#
Code |
Name |
Due |
Previously |
---|---|---|---|
LDM-503-11a |
ComCam Ops Readiness |
2020-12-31 |
Completed |
EPO-M6 |
User Interfaces Complete |
2022-09-30 |
Completed |
EPOC304 |
Citizen Science Commissioning Project running via LSST infrastructure Complete |
2022-09-30 |
Completed |
SITCOM-92 |
Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope |
2022-12-01 |
Completed |
LDM-503-13 |
Ops rehearsal for data release processing #1 |
2023-02-28 |
Completed |
DM-27734 |
Completion of the Scheduler |
2023-06-30 |
Completed |
SITCOM-127 |
M2 coating decision |
2023-10-01 |
Completed |
LSST4820 |
Love Contract Complete |
2023-11-01 |
Completed |
DM-35987 |
OCS Available on Summit |
2024-02-01 |
2024-01-02 |
DM-35989 |
TCS Demonstrated |
2024-02-01 |
2024-01-02 |
SITCOM-102 |
TMA safe for transition to M1M3 glass mirror |
2024-02-01 |
2024-01-02 |
SITCOM-97 |
M1M3 cell+Surrogate Dynamic Testing on TMA done |
2024-02-01 |
2024-02-05 |
SITCOM-105 |
ComCam + PF re-Installed on TMA |
2024-02-02 |
2024-01-03 |
SUMMIT-2976 |
LSSTCam Received @ Summit |
2024-05-15 |
2024-04-23 |
SITCOM-104 |
M2 Glass installed on Cell |
2024-05-15 |
2024-05-23 |
DM-35988 |
M2 Software demonstrated |
2024-06-03 |
2024-05-02 |
SITCOM-109 |
M1M3 Mirror Coating completed |
2024-06-07 |
2024-06-24 |
T&SC-1100-0300 |
M2 Installed on Telescope |
2024-06-20 |
2024-06-11 |
SITCOM-110 |
M1M3 installed on the TMA |
2024-07-05 |
2024-07-22 |
SITCOM-125 |
LSSTCam reverification complete |
2024-10-08 |
2024-09-17 |
SITCOM-123 |
LSSTCam Installed on TMA |
2024-11-20 |
2025-01-29 |
New1135 |
LSSTCam Cold |
2025-01-07 |
2025-02-12 |
SUMMIT-3023 |
COMP: TMA Refrigeration Tests Complete |
2025-01-29 |
2025-01-29 |
New1110 |
Full focal plane readout complete |
2025-01-30 |
2025-03-07 |
New1165 |
Telescope Aligned |
2025-01-31 |
2025-03-10 |
DM-AP-17 |
Solar System Processing pipeline (SSP) available. |
2025-02-27 |
2025-04-04 |
SITCOM-116 |
Initial Optical testing on TMA complete |
2025-02-27 |
2025-04-04 |
SITCOM-121 |
System First Light with LSSTCam |
2025-02-27 |
2025-04-04 |
COMC-0140 |
Start SV Data Collection |
2025-04-04 |
2025-05-12 |
DM-AP-16 |
Full integration of the Alert Production system within the operational environment. |
2025-06-25 |
2025-07-31 |
LDM-503-16 |
Ops rehearsal for data processing #3 |
2025-07-02 |
2025-08-07 |
Download the PDF of this Block Schedule here.
Acronym |
Description |
---|---|
AI |
Artificial Intelligence |
AI&T |
Assembly Integration & Test |
AP |
Alert Production |
CCW |
Camera Cable Wrap |
COMP |
COMPlete |
ComCam |
The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. |
DM |
Data Management |
EPO |
Education and Public Outreach |
HTML |
HyperText Markup Language |
LDM |
LSST Data Management (Document Handle) |
LSST |
Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) |
M1M3 |
Primary Mirror Tertiary Mirror |
M2 |
Secondary Mirror |
OCS |
Observatory Control System |
Portable Document Format |
|
SC |
System Commissioning |
SITCOM |
System Integration, Test and Commissioning |
SLAC |
SLAC National Accelerator Laboratory |
SSP |
Solar System Processing |
SV |
Science Validation |
TCS |
Telescope Control System |
TMA |
Telescope Mount Assembly |