| Due | Name |
|---|---|
| 30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
| 31-Mar-2023 | TMA Handoff to Rubin (Completed 31-Mar-2023) |
| 26-Mar-2024 | COMP: Camera Pre-Ship Review at SLAC |
| 17-Jun-2024 | ComCam Reinstalled on TMA |
| 01-Jul-2024 | Dome Complete |
| 22-Jul-2024 | 3-Mirror Optical System Ready for Testing |
| 27-Sep-2024 | Camera Ready for Full System AI&T |
| 03-Jan-2025 | LSSTCam Ready for On Sky (First Photon) |
| 18-Feb-2025 | System First Light with LSSTCam |
| 16-Jun-2025 | Test report: Final Pipelines Delivery |
| 16-Jun-2025 | COMP: Science Validation Surveys Complete |
| 23-Jun-2025 | Operation Readiness Review Complete |
Using December 2023 project controls data.