Celebratory Milestones#
- tocdepth:
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version 671aa73a, dated 2024-01-22. This corresponds to the status recorded in the project controls system for December 2023.
Top milestones#
2022-09-30 : EPO Construction Finish (EPOC285) Completed 2022-09-30
2023-03-31 : TMA Handoff to Rubin (T&SC-0400-1730) Completed 2023-03-31
2024-03-26 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
2024-06-17 : ComCam Reinstalled on TMA (SUMMIT-Oct24-160)
2024-07-01 : Dome Complete (T&SC-0400-0950)
2024-07-22 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
2024-09-27 : Camera Ready for Full System AI&T (COMC-060200-20930)
2025-01-03 : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)
2025-02-18 : System First Light with LSSTCam (LSST-1520)
2025-06-16 : Test report: Final Pipelines Delivery (LDM-503-17a)
2025-06-16 : COMP: Science Validation Surveys Complete (COMC-0654-0430)
2025-06-23 : Operation Readiness Review Complete (SITCOM-130)
A public HTML version for embedding is here.
Supporting milestones#
2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
2022-12-01 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92) Completed 2022-12-01
2023-02-28 : Ops rehearsal for data release processing #1 (LDM-503-13) Completed 2023-02-28
2023-06-30 : Completion of the Scheduler (DM-27734) Completed 2023-06-30
2023-10-01 : M2 coating decision (SITCOM-127) Completed 2023-10-01
2023-11-01 : Love Contract Complete (LSST4820) Completed 2023-11-01
2024-01-02 : OCS Available on Summit (DM-35987)
2024-01-02 : TCS Demonstrated (DM-35989)
2024-01-03 : ComCam + PF re-Installed on TMA (SITCOM-105)
2024-01-08 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
2024-02-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
2024-04-23 : LSSTCam Received @ Summit (SUMMIT-2976)
2024-05-02 : M2 Software demonstrated (DM-35988)
2024-05-08 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
2024-05-23 : M2 Glass installed on Cell (SITCOM-104)
2024-06-11 : M2 Installed on Telescope (T&SC-1100-0300)
2024-06-24 : M1M3 Mirror Coating completed (SITCOM-109)
2024-07-22 : M1M3 installed on the TMA (SITCOM-110)
2024-09-27 : LSSTCam reverification complete (SITCOM-125)
2024-11-11 : LSSTCam Installed on TMA (SITCOM-123)
2024-12-27 : LSSTCam Cold (New1135)
2025-01-21 : Full focal plane readout complete (New1110)
2025-01-22 : Telescope Aligned (New1165)
2025-02-18 : Solar System Processing pipeline (SSP) available. (DM-AP-17)
2025-02-18 : Initial Optical testing on TMA complete (SITCOM-116)
2025-02-18 : System First Light with LSSTCam (SITCOM-121)
2025-03-26 : Start SV Data Collection (COMC-0140)
2025-06-16 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
2025-06-23 : Ops rehearsal for data processing #3 (LDM-503-16)
Download the PDF of this Block Schedule here.
Acronym |
Description |
---|---|
AI |
Artificial Intelligence |
AI&T |
Assembly Integration & Test |
AP |
Alert Production |
CCW |
Camera Cable Wrap |
COMP |
COMPlete |
ComCam |
The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. |
DM |
Data Management |
EPO |
Education and Public Outreach |
HTML |
HyperText Markup Language |
LDM |
LSST Data Management (Document Handle) |
LSST |
Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) |
M1M3 |
Primary Mirror Tertiary Mirror |
M2 |
Secondary Mirror |
OCS |
Observatory Control System |
Portable Document Format |
|
SC |
System Commissioning |
SITCOM |
System Integration, Test and Commissioning |
SLAC |
SLAC National Accelerator Laboratory |
SSP |
Solar System Processing |
SV |
Science Validation |
TCS |
Telescope Control System |
TMA |
Telescope Mount Assembly |