Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
31-Mar-2023 | TMA Handoff to Rubin (Completed 31-Mar-2023) |
21-Feb-2024 | COMP: Camera Pre-Ship Review at SLAC |
29-May-2024 | ComCam Reinstalled on TMA |
01-Jul-2024 | Dome Complete |
03-Jul-2024 | 3-Mirror Optical System Ready for Testing |
28-Aug-2024 | Camera Ready for Full System AI&T |
11-Dec-2024 | LSSTCam Ready for On Sky (First Photon) |
24-Jan-2025 | System First Light with LSSTCam |
22-May-2025 | Test report: Final Pipelines Delivery |
22-May-2025 | COMP: Science Validation Surveys Complete |
29-May-2025 | Operation Readiness Review Complete |
Using September 2023 project controls data.