Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
28-Feb-2023 | TMA Handoff to Rubin |
21-Jun-2023 | COMP: Camera Pre-Ship Review at SLAC |
04-Apr-2024 | Camera Ready for Full System AI&T |
18-Apr-2024 | Dome Complete |
20-May-2024 | 3-Mirror Optical System Ready for Testing |
28-Jun-2024 | LSSTCam Ready for On Sky (First Photon) |
08-Oct-2024 | System First Light |
03-Feb-2025 | Test report: Final Pipelines Delivery |
03-Feb-2025 | COMP: Science Validation Surveys Complete |
10-Feb-2025 | Operation Readiness Review Complete |
Using March 2023 project controls data.