Due | Name |
---|---|
03-Oct-2022 | DELETE Engineering First Light w/ComCam |
16-Jan-2023 | TMA Contract Complete |
16-Jan-2023 | TMA Handoff to Rubin |
12-May-2023 | COMP: Camera Pre-Ship Review at SLAC |
29-Sep-2023 | EPO Construction Finish |
05-Dec-2023 | Camera Ready for Full System AI&T |
21-Dec-2023 | Dome Complete |
15-Mar-2024 | 3-Mirror Optical System Ready for Testing |
15-Jul-2024 | System First Light |
08-Nov-2024 | Test report: Final Pipelines Delivery |
08-Nov-2024 | Mini-Survey 2 Complete |
15-Nov-2024 | Operation Readiness Review Complete |
Using October 2022 project controls data.