DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
31-Mar-2023 TMA Handoff to Rubin (Completed 31-Mar-2023)
21-Feb-2024 COMP: Camera Pre-Ship Review at SLAC
29-May-2024 ComCam Reinstalled on TMA
01-Jul-2024 Dome Complete
03-Jul-2024 3-Mirror Optical System Ready for Testing
28-Aug-2024 Camera Ready for Full System AI&T
11-Dec-2024 LSSTCam Ready for On Sky (First Photon)
24-Jan-2025 System First Light with LSSTCam
22-May-2025 Test report: Final Pipelines Delivery
22-May-2025 COMP: Science Validation Surveys Complete
29-May-2025 Operation Readiness Review Complete

Using September 2023 project controls data.