Due | Name |
---|---|
02-Dec-2022 | EPO Construction Finish |
16-Dec-2022 | Beneficial occupancy of the TMA |
16-Dec-2022 | TMA Handoff to Rubin |
12-May-2023 | COMP: Camera Pre-Ship Review at SLAC |
08-Nov-2023 | 3-Mirror Optical System Ready for Testing |
29-Nov-2023 | Engineering First Light w/ComCam |
21-Dec-2023 | Dome Complete |
14-Feb-2024 | Camera Ready for Full System AI&T |
19-Jul-2024 | System First Light |
14-Nov-2024 | Test report: Final Pipelines Delivery |
14-Nov-2024 | Mini-Survey 2 Complete |
21-Nov-2024 | Operation Readiness Review Complete |
Using October 2022 project controls data.