Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
31-Mar-2023 | TMA Handoff to Rubin (Completed 31-Mar-2023) |
26-Mar-2024 | COMP: Camera Pre-Ship Review at SLAC |
17-Jun-2024 | ComCam Reinstalled on TMA |
22-Jul-2024 | 3-Mirror Optical System Ready for Testing |
17-Sep-2024 | Camera Ready for Full System AI&T |
16-Dec-2024 | Dome Complete |
19-Feb-2025 | LSSTCam Ready for On Sky (First Photon) |
04-Apr-2025 | System First Light with LSSTCam |
31-Jul-2025 | Test report: Final Pipelines Delivery |
31-Jul-2025 | COMP: Science Validation Surveys Complete |
07-Aug-2025 | Operation Readiness Review Complete |
Using December 2023 project controls data.