| Due | Name |
|---|---|
| 24-Oct-2022 | Engineering First Light w/ComCam |
| 16-Jan-2023 | TMA Contract Complete |
| 16-Jan-2023 | TMA Handoff to Rubin |
| 03-Feb-2023 | EPO Construction Finish |
| 12-May-2023 | COMP: Camera Pre-Ship Review at SLAC |
| 05-Dec-2023 | Camera Ready for Full System AI&T |
| 21-Dec-2023 | Dome Complete |
| 26-Jan-2024 | 3-Mirror Optical System Ready for Testing |
| 15-Jul-2024 | System First Light |
| 08-Nov-2024 | Test report: Final Pipelines Delivery |
| 08-Nov-2024 | Mini-Survey 2 Complete |
| 18-Nov-2024 | Operation Readiness Review Complete |
Using October 2022 project controls data.