DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2022-11-17

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version 6a649f25, dated 2022-11-17. This corresponds to the status recorded in the project controls system for October 2022. This compares milestones/data/pmcs/202209-ME.xls to 202210-OCTSANDBOXV2.xls.

Top milestones

  • 2023-07-20-> 2022-10-24 : Engineering First Light w/ComCam (LSST-1513)
  • 2022-11-02-> 2023-01-16 : TMA Contract Complete (T&SC-1404-0750)
  • None-> 2023-01-16 : TMA Handoff to Rubin (T&SC-0400-1730)
  • 2022-12-02-> 2023-02-03 : EPO Construction Finish (EPOC285)
  • 2023-05-01-> 2023-05-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-10-17-> 2023-12-05 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2023-03-29-> 2023-12-21 : Dome Complete (T&SC-0400-0950)
  • 2023-06-14-> 2024-01-26 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-03-14-> 2024-07-15 : System First Light (LSST-1520)
  • 2024-07-10-> 2024-11-08 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-07-10-> 2024-11-08 : Mini-Survey 2 Complete (COMC-0654-0430)
  • 2024-07-17-> 2024-11-18 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31-> 2020-12-31 : ComCam Ops Readiness (LDM-503-11a)
  • 2023-06-30-> 2022-10-03 : Ops rehearsal for data release processing #1 (ComCam data) (LDM-503-13)
  • 2022-09-01-> 2022-10-03 : Completion of the Scheduler (DM-27734)
  • 2023-10-13-> 2022-10-03 : M2 coating decision (SITCOM-127)
  • 2022-11-15-> 2022-10-03 : M2 Glass installed on Cell (SITCOM-104)
  • 2022-10-06-> 2022-10-06 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2023-07-20-> 2022-10-24 : Start SV Data Collection (COMC-0140)
  • 2022-09-30-> 2022-10-31 : User Interfaces Complete (EPO-M6)
  • 2022-09-30-> 2022-10-31 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304)
  • 2022-10-17-> 2022-11-17 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2022-12-28-> 2022-12-28 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2023-01-09-> 2023-02-07 : M2 Software demonstrated (DM-35988)
  • 2023-09-14-> 2023-03-14 : Optical testing on TMA complete (SITCOM-116)
  • 2023-02-14-> 2023-03-15 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-01-03-> 2023-04-19 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-05-31-> 2023-05-31 : OCS Available on Summit (DM-35987)
  • 2023-05-31-> 2023-05-31 : TCS Demonstrated (DM-35989)
  • 2023-05-24-> 2023-06-07 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-06-02-> 2023-07-04 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-02-07-> 2023-07-21 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-10-03-> 2023-11-01 : Love Contract Complete (LSST4820)
  • 2023-10-17-> 2023-12-05 : LSSTCam reverification complete (SITCOM-125)
  • 2023-06-14-> 2024-01-26 : M1M3 installed on the TMA (SITCOM-110)
  • 2024-01-12-> 2024-02-16 : LSSTCam Installed on TMA (SITCOM-123)
  • None-> 2024-04-04 : LSSTCam Cold (New1135)
  • None-> 2024-04-22 : Full focal plane readout complete (New1110)
  • None-> 2024-05-13 : Telescope Aligned (New1165)
  • 2024-03-14-> 2024-07-15 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-03-14-> 2024-07-15 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-07-10-> 2024-11-08 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly