DueName
16-Dec-2022 TMA Contract Complete
16-Dec-2022 TMA Handoff to Rubin
03-Feb-2023 EPO Construction Finish
12-May-2023 COMP: Camera Pre-Ship Review at SLAC
21-Dec-2023 Dome Complete
14-Feb-2024 3-Mirror Optical System Ready for Testing
06-Mar-2024 Engineering First Light w/ComCam
17-May-2024 Camera Ready for Full System AI&T
22-Oct-2024 System First Light
17-Feb-2025 Test report: Final Pipelines Delivery
17-Feb-2025 Mini-Survey 2 Complete
24-Feb-2025 Operation Readiness Review Complete

Using October 2022 project controls data.